Falls on the level
Falls on the level is its own registered hazard type, covering level changes of 300mm or less, including falls associated with baths. It shares its capture module with falling on stairs and falling between levels, but is scored, triaged and reported as a distinct hazard.
What it is
The GOV.UK guidance groups this with bath-related falls specifically: grab rail presence and slip resistance in the bath or shower sit alongside level-change and threshold checks. Falls on the level is a Phase 2 hazard: capturable in full, with its statutory clock applying to non-emergency cases reported on or after 30 November 2026; an emergency case is covered by Phase 1 whenever it was reported.
How to do it
- On the Falls card, record stairs condition, handrail presence and condition, and balustrade/guarding condition where relevant to the property.
- Record whether the worst level change measured exceeds 300mm, plus bath and shower grab-rail presence and slip resistance.
- Record window restrictor presence and whether they’re working, and the measured drop height and landing-surface hardness for any relevant edge.
- Complete Hazard Triage, citing GOV.UK’s own prompt questions: is a fall likely given the property’s condition and the household’s vulnerabilities (60 and over, mobility or sensory impairment), and what would the consequences of a fall actually be?
How it integrates
All three falls hazard types share one AI preset (housing-falls): image analysis restates only what’s visible (a stair or handrail defect, missing guarding, a level change, an absent grab rail, a slip-risk surface, a window restrictor issue, or an open drop) never a guarding-height or drop-height measurement, and never a fall-likelihood judgement, which stays yours. The finished record uses the “Falls Hazard Assessment Report” template. Everyday trips and slips unrelated to a building defect, ladder or furniture misuse, and tenant-caused landscaping damage are explicitly out of GOV.UK’s scope for this hazard.
Common problems
- I only see one “Falls” section for three hazard types. Expected. The capture module is shared, but each survey is scored and reported against the single falls profile chosen for that job.
- There’s no due date on this job. Expected for a non-emergency case reported before 30 November 2026, Phase 2’s start date.
- A trip on a rug or loose furniture came up on-site. That’s out of GOV.UK’s scope for this hazard unless it stems from a building defect.
Related